Wednesday 4 August 2010

The Day Before

Preparation for pod install.

Slate roof covering is stripped and most of the structure is removed except for timber purlins and binders.

Pad stone positions are checked against drawings and set in place.



There is some concern as existing wall plate levels indicate a 40mm difference on front elevation.

Concrete pad stones set on rapid hardening mortar. In the end the rear pad stones are substituted with a full length concrete lintel due to the two openings for rear bedroom and door way to bath room.


Pod being loaded.