Friday 3 September 2010

Roof complete

Roof covering work is complete!!!

Vents for MVHR exhaust and intake from outside appear to be too close together.


Confirmed with suppler of the solution to have top vent as the exhaust. This solution should be adequate.

Brackets supplied for solar hot water panels are for a tiled roof not a slated.

Contacted supplier unfortunately cannot get the correct brackets to us soon enough. Requested manufacturer drawings for the brackets. Steel fabricators asked to make up brackets over night.

The roof recovering works have take longer than desired. With hindsight we would have requested a gang to carry out works over a week rather than one operative taking three weeks. Nevertheless finished product is good.