Decoration complete.
Minor finishing off tasks have dragged on a little, but we are there.
Property complete.
Wednesday, 24 November 2010
Friday, 19 November 2010
I'm sure I can see the finish?
Heating install completed and commissioned.
Some minor commissioning issues with a leak on solar pipes on the roof. This was easily addressed.
Wattbox second fix complete and commissioned.
Operating as planned.
External works complete.
Some minor commissioning issues with a leak on solar pipes on the roof. This was easily addressed.
Wattbox second fix complete and commissioned.
Operating as planned.
External works complete.
Thursday, 11 November 2010
Still 2nd fixing
Second fix work continues.
Some electric cables were lost while boarding over ceilings and walls. This caused some minor opening up to re locate cables, in two or three locations.
Decoration continues.
Some electric cables were lost while boarding over ceilings and walls. This caused some minor opening up to re locate cables, in two or three locations.
Decoration continues.
Friday, 5 November 2010
2nd Fix Electrics
Second fix electrics commenced.
There was some ambiguity with regards to the securing of the light fittings which was clarified by the lighting supplier.
The down-lights in the pod were substituted for surface light fittings. Although not an ideal solution, it was adequate.
Internal decoration commenced on site. Although this was a little premature, we needed to gain some time back.
There was some ambiguity with regards to the securing of the light fittings which was clarified by the lighting supplier.
The down-lights in the pod were substituted for surface light fittings. Although not an ideal solution, it was adequate.
Internal decoration commenced on site. Although this was a little premature, we needed to gain some time back.
Wednesday, 3 November 2010
Waterproof testing