Second fix electrics commenced.
There was some ambiguity with regards to the securing of the light fittings which was clarified by the lighting supplier.
The down-lights in the pod were substituted for surface light fittings. Although not an ideal solution, it was adequate.
Internal decoration commenced on site. Although this was a little premature, we needed to gain some time back.